New 5,000,000 gallon sewer overflow tank with detached electrical building and all associated piping.
Projects
New 5,000,000 gallon sewer overflow tank with detached electrical building and all associated piping.
To increase production capacity and provide capital improvements, Kerry Ingredients, Inc. contracted J. Cumby Construction to Expand their Liquid Smoke manufacturing plant in Monterey, TN. Included in the scope was the construction of a new truck scale, a replacement of the truck ramp, dump, and hopper structures, a sawdust storage silo, various improvements to site structures, significant soil remediation, and four new building structures to include, an electrical building, control room, burner equipment building, and wet storage tank building.
Location: Monterey, TN
Completion Date: May 2019
$3,200,000+ Contract Value
Owner: Kerry Ingredients & Flavours
Bouton Engineering, Gary Bouton
2,100 CY of Concrete
18,000 Tons of Stone
Construction of a new sewer pump station for the city of Decatur, AL.
The Terris Tatum project in Madison, AL consists of a new raw water intake and pumping station on the Tennessee River.
This Water Treatment Plant Improvements project consists of a new sodium hypochlorite building and sodium hypochlorite system used to treat water prior to distribution to residents of Rutherford County, TN.
A new construction project for Tigar International to include ample warehouse space for product distribution and adequate office space.
The design-build warehouse addition at Tenneco Automotive in Smithville, TN created additional space for storage of new automotive parts manufactured at the facility, a new dock area for shipping products, and access to the new facilities.
The Jobe/Murphy Residence Hall Upgrade was a complete renovation of two dorm facilities on the campus of Tennessee Technological University.
A new submersible sewage pump station located on the same sites as the existing Mayberry Street lift station, South Carter Street lift station, and Turn Table Road lift station.
This new construction of an Optometry office for Drs. Zach & Lori Boyd focuses on offering more room for patients before, during, and after their examinations.
This automotive, semi-truck and RV repair shop includes a showroom and display area for RV sales, maintenance area with multiple bays and office space.
This expansion included additional classrooms, bathrooms and storage, a new coffee bar and gathering area – all built with future growth in mind.
This addition includes a new Sodium Hypochlorite Feed Building and a 5,500 square foot stand-alone structure with a major focus on the subsurface conditions.
This project included the installation of a new headworks structure and influent pump station. The main challenge of this project was the dewatering need for construction.
This project involved new influent headworks, influent pump station, SDADA, metering system, disinfection structures, chemical feed systems, and a maintenance building.
The Cottage is a multi-bed, assisted living center with full bedrooms, private bathrooms, two kitchens, dining areas, two dens, a spa, and in-house laundry.
This addition included new classrooms, upgrades to the existing facilities, a new FEMA storm shelter, a remodel of the existing cafeteria, reroofing, and infrastructure upgrades
This construction included a new oxidation ditch, flow equalization and RAS pump stations, chlorine analyzer, laboratory building, sludge bed modifications and more.