J Cumby Construction, Inc., will be making modifications to the existing equalization basins to include construction of a dividing wall in each existing equalization basin, which is in excess of 7 acres each, to result in four (4) new basins at the end of construction, demolition of existing process equipment and installation of new diffusers, aerators, vertical turbine pumps, blowers, water cannons with associated piping and electrical infrastructure, demolition and renovation of portions of the plan blower building and a dilution water pump station. Additionally, there will be resurfacing and repairs made to the asphalt around the equalization basins.
Furthermore, there will be approximately 10,000 cubic yards of concrete needed in order to complete the project. In Addition, the City of Chattanooga will be coordinating with J Cumby to plan out phases in which the modifications will be completed. The City of Chattanooga is needing the equalization basins to remain operational throughout the project to ensure that the WWTP can meet the system demands, as well as making sure the project can be completed on time.
PROJECT INFORMATION:
Location: Chattanooga, TN
Date Completed (Estimated): August, 2023
Contract Value of $27,685,000+
Owner: City of Chattanooga
Engineer: Jacobs
NOTABLE SPECS:
Approximately 10,000 Cubic Yards of concrete will be required to complete this project
The Equalization basins are required to remain operational throughout the project